What is actually in the yard?
Identify the shield by its markings and compare the components in the yard with the parts list for the planned arrangement. A manual for the right family can still describe a different build; a spreader that fits between the panels need not be the one specified. [1] [2] [3]
Manual, configuration and parts
A photograph can show what is present without telling you what belongs. Compare the unit marking and side arrangement with the manual’s coverage before treating a pin, keeper or other loose part as an item from that assembly. [2] [3]
Match the marking to the document’s covered models. GME’s Build-A-Box brochure, for example, describes two-, three-, four- and eight-sided family arrangements and names pins and keepers. A photo of one arrangement is not the parts list for another. Record the applicable list, identify anything missing or substituted and leave the discrepancy open. [3] [2]
For a design based on manufacturer’s tabulated data, follow the specifications, recommendations and limitations. Any deviation needs specific written approval from the manufacturer. Keep a written copy of the data and any such approval at the site during construction of the protective system. [2]
Record the location of damage separately from a decision on suitability. Damaged protective-system equipment goes to the competent person for examination. If that person cannot assure suitability, remove it from service; a registered professional engineer must evaluate and approve it before return. [2]
Site, lift and access evidence
For each underground installation, record the utility owner contacted, response, estimated position, and where the exact location has been determined by safe and acceptable means as work approaches. Identify water, adjacent structures, spoil and equipment loads, and the person responsible for checking changes. An unanswered locate request is not confirmation of a clear area. [1]
Use the actual assembled weight, handling instructions, designated lift points and the chart for the machine and planned movement. Identify who keeps people clear: no one under a load handled by lifting or digging equipment, and no employees in a shield while it is being installed, removed or moved vertically. Separately record the protected entry and exit route. In trenches at least four feet deep, no employee may need to travel more than 25 feet laterally to a safe means of egress. [1] [2] [3]
At shift change
Name the competent person for the incoming shift. Where employee exposure can reasonably be anticipated, inspections cover the excavation, adjacent areas and protective systems before work starts, as needed during the shift, and after rainstorms or other hazard-increasing events. Pass on observations, corrective measures and unresolved items by name. If evidence of a hazardous condition is found, remove exposed employees until the necessary precautions are taken. [1]
Sources
- 29 CFR 1926.651: Specific excavation requirementsOccupational Safety and Health Administration
- 29 CFR 1926.652: Requirements for protective systemsOccupational Safety and Health Administration
- Build-A-Box Modular Aluminum Trench Shielding System — features and assemblyGriswold Machine & Engineering / Arcosa Shoring Products