What must the system do?
One way to read the comparison is to ask what changes physically. A bench changes the face itself; a shore supports the face; a shield can protect people within it without providing that support. [1] [3]
| Method | Function | Space needed | Ground or adjacent structure | Design record |
|---|---|---|---|---|
| Sloping | Cut the face back on an incline | Room beyond the bottom footprint | Can the face be cut back without undermining a foundation? | §1926.652(b); check the applicable slope configuration and depth limit |
| Benching | Cut horizontal levels into the face | Room for steps as well as the work area | Does the design permit steps in this soil? Appendix B does not show benches for Type C. | §1926.652(b); match soil, geometry and depth to design |
| Shoring | Support excavation sides against movement | Room for shores, braces and work between them | Which ground or adjoining installation needs support? Does it need separate underpinning? | §1926.652(c); match support members and layout to governing data or design |
| Shielding | Withstand cave-in forces and protect workers inside | Room for the complete shield and the work inside it | What remains outside the shield? Do not count it as foundation support. | §1926.652(c); identified shield, configuration and load limits |
Depth check for both sloping and benching: §1926.652(b)(2) points to Appendices A and B. For an excavation greater than 20 feet deep, read Appendix B, Table B-1, note 3 for its professional-engineer design requirement rather than extending a shallower table configuration. [3]
Compare the footprint with what must remain stable
Sloping and benching need room at the surface beyond the bottom of the excavation. A roadway or property boundary may rule out that footprint. In a narrower cut, shoring and shielding still need enough room for the members and for the equipment that will place them. [1] [3]
For example, a shield may leave enough room for a crew to join pipe beside a building. That answers a workspace question. If excavation could endanger the footing, the employer still needs to address stability under §1926.651(i); increasing the shield’s interior clearance does not support the footing. [1] [2]
Choose the design record for the method
Sloping and benching designs follow one of four routes: a default slope no steeper than one and a half horizontal to one vertical, 34 degrees from horizontal, with Type C configurations from Appendix B; the tables in Appendices A and B; other written tabulated data; or a registered professional engineer's design. The engineer's written design must state the slope magnitudes and configurations found safe, identify the engineer, and stay on site while the slope is built. [3]
For support and shield systems, §1926.652(c) provides design options that depend on the system. The appendix route addresses timber and aluminum hydraulic shoring. Shield designs use manufacturer data, other engineer-approved tabulated data or a registered professional engineer’s design. [3]
The manufacturer's data impose strict installation and use limits, so they must be read closely. A system drawn from that data must be installed in line with all of the manufacturer's specifications, recommendations and limitations, and any deviation needs the manufacturer's specific written approval. The written data must be at the jobsite during construction of the trench system. Damaged components must be examined by a competent person and, where suitability cannot be assured, removed from service until a registered professional engineer evaluates and approves them. [3]
Site hazards common to all four methods
Surface housekeeping is regulated separately from the method choice. Excavated dirt and equipment that could fall or roll into an excavation must be kept at least two feet from the edge, held back by retaining devices, or both. NIOSH's pre-job planning advice adds that trenching practices and layout should put spoil piles and heavy-equipment routes in safe positions away from the trench. [2] [4]
Record utilities, water, edge loads, traffic, vibration and adjacent structures for the site review. An exit in a trench at least four feet deep must require no more than 25 feet of lateral travel. Daily competent-person inspections, including after rain or another hazard-increasing event when exposure is reasonably anticipated, do not replace the method-specific design. [2]
Sources
- 29 CFR 1926.650: Scope, application, and definitions applicable to this subpartOccupational Safety and Health Administration
- 29 CFR 1926.651: Specific excavation requirementsOccupational Safety and Health Administration
- 29 CFR 1926.652: Requirements for protective systemsOccupational Safety and Health Administration
- Preventing Worker Deaths from Trench Cave-ins (NIOSH Workplace Solutions 2011-208)CDC and NIOSH