What to Establish Before Planning Trench Protection

The route, utilities, ground, water, nearby foundations and access affect the choice of protection. Different people can verify different parts of the plan.

Updated November 20, 20263 min read

The proposed work and its limits

Before comparing methods, establish where the work will take place, what the crew must do and what is known about the excavation. A proposed route or planned depth is not an observation of conditions on site. [4]

Planning the excavation around existing utilities

Underground installations carry the most consequential early questions. The standard requires the estimated location of underground utilities and services—sewer, telephone, fuel, electric and water lines, or other underground installations reasonably expected during excavation—to be determined before an excavation is opened. Utility companies or owners must be contacted within established or customary local response times, advised of the proposed work, and asked to establish the location before digging starts. [2]

The standard also covers an unanswered locate request. Where utility companies or owners cannot respond within 24 hours, unless state or local law sets a longer period, or cannot establish the exact location, the employer may proceed with caution, using detection equipment or other acceptable means to locate the installations. As excavation approaches the estimated location, the exact location must be determined by safe and acceptable means. [2]

Geometry and water

Length, width and depth describe the proposed opening. Compare them with the space people and equipment will actually need, including the approach to the work position. [1]

Accumulated or accumulating water can expose workers to hazards that a shield alone does not address. Adequate precautions are required; where water-removal equipment is used to prevent or control accumulation, a competent person must monitor it and the operations. [2]

Excavation beside a building or foundation

Adjoining building walls, foundations and other structures need a recorded interface in the excavation site planning notes. Where excavation endangers their stability, support systems such as shoring, bracing or underpinning must be provided. Excavation below the base or footing of a foundation or retaining wall that could reasonably be expected to pose a hazard is not permitted unless one of the standard's conditions applies: a support system, stable rock, or a registered professional engineer's approved determination that the structure is sufficiently removed or that the work will not pose a hazard. Sidewalks, pavements and appurtenant structures in the area must not be undermined unless a support system or another method of protection is provided. [2]

Access for workers and equipment

Record whether the proposed excavation ramp will carry workers or equipment. Mark where workers will enter the excavation and how equipment will reach the ramp. [2]

Walkways are required where employees or equipment cross an excavation, with guardrails where the walkway is 6 feet or more above lower levels. [2]

Who can answer which question?

A utility owner can supply information about its service. That information cannot replace a competent person’s inspection or a manufacturer’s written approval for a departure from its data. [1] [2] [3]

The roles map pairs utility information with the owner or operator, hazard inspection with the competent person, and departures from manufacturer data with that manufacturer.Utility owner or operatorProvide location information for the affectedinstallation.Competent personIdentify hazards and exercise authority tocorrect them.ManufacturerGive specific written approval for a departurefrom its data.
Utility location, field inspection and design departures.

The utility owner or operator can help identify a service. The competent person inspects for hazards and has authority to act on them. Neither role gives someone authority to approve a departure from a manufacturer’s tabulated data on the manufacturer’s behalf. [1] [2] [3] [4]

Excavation equipment and manufacturer questions need the exact document, not a family description. Where a system is drawn from manufacturer's tabulated data, the design must follow all specifications, recommendations and limitations issued by the manufacturer, deviation is allowed only after the manufacturer issues specific written approval, and those documents must be in written form at the jobsite during construction of the protective system. [3]

Sources

  1. 29 CFR 1926.650: Scope, application, and definitions applicable to this subpartOccupational Safety and Health Administration
  2. 29 CFR 1926.651: Specific excavation requirementsOccupational Safety and Health Administration
  3. 29 CFR 1926.652: Requirements for protective systemsOccupational Safety and Health Administration
  4. Preventing Worker Deaths from Trench Cave-ins (NIOSH Workplace Solutions 2011-208)CDC and NIOSH