What the delivery establishes
A delivered box can arrive with some hardware attached and other parts shipped separately. Receiving confirms what is physically present. It does not establish that the parts form the approved arrangement. [1]
Match the documents to the unit
Compare the manufacturer, model and unit markings on the equipment with the paperwork. If the supplier’s description differs, preserve both identities until the source of the difference is known. [4] [3]
The record must belong to the equipment. OSHA defines tabulated data as tables and charts approved by a registered professional engineer and used to design and construct protective systems, and the manufacturer's-data route calls for adherence to all issued specifications, recommendations and limitations. A family landing page, general guidelines, a URL slug or an internal plan is not evidence of what a particular trench box is rated to do at a given excavation depth or in a given soil type, and none of them shows compliance with the requirements for that trench box in a trench. [1] [3]
Match Supplied Parts to the Documented Arrangement
With the document identified, compare it line by line against the shipment: the members present, the spreaders, the pins and keepers, and any other part the sheet lists as required. Three outcomes are possible, a match, a mismatch, or an item that cannot be checked because a part or document is missing, and each deserves its own note rather than a single tick. [4] [3]
Substitution falls outside receiving authority. Under OSHA's manufacturer-tabulated-data option, departing from the manufacturer's specifications, recommendations or limitations is allowed only after the manufacturer issues specific written approval. A receiver who fits a different spreader pipe or a shop-made pin has changed the configuration, and the document on file no longer describes the trench box set between the trench walls. [3]
Example: Pro-Tec spreaders and pins
A receiving note that says ‘pins included’ answers a packing question. To answer the configuration question, the receiver also needs the identification that ties those pins and keepers to the arrangement on the shield's own sheet. [4] [3]
Pro-Tec says its engineer-stamped certification sheets require at least two spreader pipes on each end with the approved pins and keepers. It describes a fifth spreader as adding rigidity on larger boxes. Those details apply to the Pro-Tec example, not to every box on a delivery truck. [4]
Pro-Tec also sends exceptions back to the sheet: specially designed shields needing five or more spreaders, or pipe of a different specification such as 10-inch schedule 120, are to be checked against the certification sheet. For a receiver that is a prompt to find the unit-specific document, not to apply a general rule about how many spreaders a box should carry. [4]
Damage is a separate finding
Concrete observations work best: deformation of the side walls, a crushed bottom edge, corrosion, missing or loose fasteners, damaged identification plates, and any component that plainly does not belong with the rest. OSHA treats failure as breakage, displacement or permanent deformation of a structural member or connection that reduces its structural integrity and supportive capability, so a bent member is a structural question rather than a cosmetic one for a worker who will enter the box. [1] [3]
Escalation for damage is prescribed, not discretionary. Under OSHA's materials-and-equipment rule for protective systems in 29 CFR 1926.652(d), damaged equipment must be examined by a competent person, who evaluates its suitability for continued use; if that person cannot assure it will support the intended loads or is otherwise suitable for safe use, the item is removed from service and must be evaluated and approved by a registered professional engineer before the trench box is returned to service. [3]
Receiving is not a site inspection
Entry inspection is a separate event with its own timing. Under OSHA's excavation requirements in 29 CFR 1926.651(k), a competent person inspects the excavation, the adjacent areas and the protective system before work starts each day, as needed through the shift, and after every rainstorm or other hazard-increasing occurrence, and removes exposed workers when there is evidence of a possible cave-in, protective-system failure, hazardous atmosphere or other hazard. A completed receiving record does not stand in for that inspection. [2]
Sources
- 29 CFR 1926.650: Scope, application, and definitions applicable to this subpartOccupational Safety and Health Administration
- 29 CFR 1926.651: Specific excavation requirementsOccupational Safety and Health Administration
- 29 CFR 1926.652: Requirements for protective systemsOccupational Safety and Health Administration
- Steel Trench ShieldsPro-Tec Equipment