Skip to content
Trench ShoringBoxes

Manhole boxes

Planning Working Space Around a Manhole Box

Compare the footprint of a manhole with the shield’s clear interior, the locations of pipe connections and ladders, and the space needed to place the structure.

Updated November 20, 20263 min read

Draw the manhole and the shield separately

The four walls in the sketch belong to the shield, not to the manhole being built. Keeping those outlines separate on the project drawing makes it easier to see which measurement describes the structure and which describes the room available inside the proposed shield. [1] [3]

Four-sided steel manhole box
The shield outline is only one of the two envelopes in a manhole fit review.

Start with the outside of the manhole or vault. Show its footprint at each elevation, including the base, wall thickness and projections. Then draw the shield around it using the dimensions for the proposed model. If installed forms or structures leave 15 feet or less between the structure and excavation side at the bottom, OSHA also classifies the excavation as a trench. [1]

A shield protects people inside it against cave-in forces. Shoring supports the excavation sides. Space inside a manhole box does not establish that the surrounding soil or a nearby foundation is supported. [1]

Separate Measured Structure Data From Assumed Clearances

The structure drawing gives the outside dimensions of the manhole. The shield drawing gives the inside dimensions of the protective box. The space left between the two is available to the crew only where pipe connections, braces and other obstructions do not occupy it. [3]

When a shield design draws on manufacturer’s tabulated data, it must follow the manufacturer’s specifications, recommendations and limitations. A proposed dimension that departs from them needs the manufacturer’s specific written approval. An assumed working clearance is an unanswered measurement question; guessing does not establish compliance or prove that a deviation has occurred. Other design routes under §1926.652(c) have their own requirements. [3]

Where pipes, ladders and lifting gear go

For each pipe connection, compare the invert and crown elevations, angle of approach, diameter and boot or sleeve with the shield openings. Can the crew make the connection from inside the protected area? Existing underground installations must also be protected, supported or removed as necessary while the excavation is open. [2]

Access shapes the layout too. In trench excavations 4 feet (1.22 m) or more deep, a stairway, ladder, ramp or other safe means of egress must be placed so workers travel no more than 25 feet (7.62 m) laterally. Record where the ladder lands once the protective system is set; a position that works in an open cut can be blocked by a panel or by the structure itself. [2]

Locate the lifting points and account for the rigging height and order of placement. Employees may not stand under loads handled by lifting or digging equipment or stay inside a shield during installation, removal or vertical movement. The installed shield must restrict hazardous movement under sudden lateral loads. [2] [3]

Utilities, equipment and nearby structures

Before excavating, identify the estimated locations of expected underground installations and contact the utilities or owners within established local response times. As work approaches a line, determine its exact location by safe and acceptable means. [2] [4]

Surface obstructions that could create a hazard must be removed or supported. Adjoining structures may need support if excavation endangers their stability, and accumulating water requires precautions to protect workers. [2]

Keep spoil and equipment that could fall or roll into the excavation at least 2 feet from the edge, restrain them, or use both measures. When mobile equipment approaches an edge the operator cannot see clearly, a warning system such as barricades, signals or stop logs is required. [2]

Depth and stacking limits

Excavating up to 2 feet below the bottom of a shield is permitted only if the shield is designed for forces calculated for the full trench depth and there are no indications, while the trench is open, of possible soil loss from behind or below it. If the proposed height requires stacked units, the manufacturer’s documentation must cover that arrangement. [3]

Sources

  1. 29 CFR 1926.650: Scope, application, and definitions applicable to this subpartOccupational Safety and Health Administration
  2. 29 CFR 1926.651: Specific excavation requirementsOccupational Safety and Health Administration
  3. 29 CFR 1926.652: Requirements for protective systemsOccupational Safety and Health Administration
  4. Preventing Worker Deaths from Trench Cave-ins (NIOSH Workplace Solutions 2011-208)CDC and NIOSH